500 kV 预制舱式变电站与常规变电站对比分析
陈 宁,孙 琛
(国网上海市电力公司超高压分公司,上海 200063)
摘 要:500 kV 崇明变电站是上海主网首个采用二次预制舱的变电站。以 500 kV 崇明变电站为例,对超高
压预制舱式变电站与常规变电站在运行环境、防水密封、暖通设计,以及消防安全等方面进行对比分析,提供
了适合于生产现场的运维策略。
关键词:预制舱式变电站;运维策略;常规变电站
作者简介:陈 宁(1974—),男,高级工程师,从事电网变电运维工作。
中图分类号:TM63 文献标志码:A 文章编号:2095-1256(2024)03-0392-03
Comparison Analysis Between 500 kV Prefabricated Substation and Conventional Substation
CHEN Ning,SUN Chen
(State Grid Extra High Voltage Branch,SMEPC,Shanghai 200063,China)
Abstract:The 500 kV Chongming Substation is the first main grid substation in Shanghai to adopt secondary pre⁃
fabricated cabins. Taking the 500 kV Chongming Substation as an example, this paper conducts a comparative
analysis between ultra-high voltage prefabricated substations and conventional substations in terms of operating
environment, waterproof sealing, HVAC design, fire safety, etc., providing operation and maintenance strate⁃
gies suitable for the production site.
Key words:prefabricated substation,operation and maintenance strategy,conventional substation
常规变电站二次设备区采用钢筋混凝土或装 运行维护策略的制定提供参数依据。
配式钢结构构造,存在建设周期长、功能区结构设
1 总体布局
计 不 合 理 、环 评 要 求 高 、粉 尘 、噪 声 及 扰 民 等 问
题,并且一二次设备必须等土建装修完工后才能 1.1 平面布置
安装,施工效率低下。预制舱式变电站集模块化、 500 kV 崇明变电站 220 kV 线路保护、母差保
智能化和经济化于一体,具有绿色环保、节能减 护、分段母联充电保护以及测控屏均布置在二次
排、高效智能等优点,较好地解决了常规变电站施 预制舱内,屏柜布置如图 1 所示,二次预制舱就地
工成本高、施工时间长、维护难度大、施工量过大、 布置于 220 kV 气体绝缘开关(GIS)设备区。与常
施工质量差等问题 [1-3] 。 规二次继电保护室相比,二次预制舱内保护测控
500 kV 崇明变电站是上海主网首个采用二 屏柜和舱体照明、暖通等同步施工、同步调试、同
次预制舱的变电站,预制舱围护结构采用新型真 步完成,施工周期大大缩短。
空隔热板和相变储能材料。新材料的应用在提供
设备可靠运行环境的基础上,有效降低了预制舱
能耗水平。本文对预制舱式变电站的结构布局、
防水密封、暖通、消防等系统进行研究,并与常规
变电站相关功能区进行分析对比,为后续预制舱 图 1 预制舱布置示意